Thursday, 19 March 2009

PERIMETER ALMOST COMPLETED



As the delivery arrived earlier than expected - breakfast time in fact - we've managed to have most of the day starting the build. We've got the sills all laid out and the perimeter almost completed. There's just one part of the perimeter to put in - it had to wait because there was an old vent cover right where it needs to go, this has been removed and the resulting hole filled.


The perimeter sections were simple to fit, just a case of screwing the sections together in the right order. Fixing of the strips which join each section was a little tricky - there must be a trick to this be we couldn't work it out and it was a bit of a struggle, they're all done now though.


Next job is to fix the last perimeter section and then fix all the frames down to the sill (after checking the level), and then on to the roof

Monday, 9 February 2009

THE STORY SO FAR











31 January/ 1 February – Had the builder round to mark out the footings and got started digging the foundations and footings. Brilliant! We discovered trees stumps and roots just below the surface which took ages to remove and then on Sunday the heavens opened and we got lots of snow which curtailed progress – well actually it got us into the house by a warm fire. Still we managed to get 3 big bags of soil dug out and. That’s about 3 cubic metres and I think we only need about 5 cubic metres out.

7 & 8 February – Nice days apart from the frost so a bit hard digging to start with! Still got on really well – almost 6 big (1 cubic yard) bags of soil now removed Early Sunday afternoon we decided it looked like we’re getting there so asked the builder to come round and have a look. BAD NEWS Seems we need to go down at least another foot and more in places– possibly as much soil as we’ve already moved to still dig out and we’re running out of room with all the soil we’ve already moved plus backs and muscles are beginning to ache!
Quick re-think needed here and we decide to let the builder finish the digging out (and disposal of the rest of the soil). Only going to cost about an £250 but I think it’ll be worth it.
FIRST LESSON. I totally underestimated the amount of soil which needed to be removed. I’ve now got to move the bags of soil to get the mini digger in.
I would advise anyone not to underestimate the task of digging the footings